James Street Club
Project Info
The works consisted of the deconstruction of the former James Street Club including removal of slab and foundations. Any basement areas to be broken out and backfilled with 6F2. All materials arising from the demolition workswere removed from site to a licensed local recycling facility. The works commenced in March 2017 and were completed in April 2017.
Client: James Street Club
Category: Building
Location: James Street club, James street, Oswaldtwistle, BB5 3LJ
Year completed: 2017
DESCRIPTION
The operations of the job were carried out as follows:
- Issue of services disconnections
- Scaffolding erected
- Erect Demarcation zones
- Removal of asbestos fuse pads
- Delivery of Skips
- General soft strip
- Removal of slates
- Delivery of machines
- Commence deconstruction
- Removal of slab and foundations
- Removal of Waste
- Backfilling of any basement areas
- Demobilisation
The works commenced in March 2017 and were completed in April 2017.